TL;DR — Quick answer

A standard store on a well-chosen theme takes 2–4 weeks. Projects with custom design and integrations take 4–8 weeks. A products-only migration of a few hundred products usually takes a few working days. Delays most often come from content (copy, photos) and feedback, not from the technical side.

The stages of building a Shopify store

StageWhat happensTypical duration
1. DiscoveryProducts, audience, goals, stores you likea few days
2. DesignTheme choice or mockups, approved before the builda few days – 2 weeks
3. SetupSettings, payments, shipping, taxes, notifications, legal pagesa few days
4. Products and contentProduct import, collections, metafields, pagesdepends on the catalogue
5. Apps and integrationsInvoicing, carriers, reviews, email, analyticsa few days
6. TestingTest orders, mobile, speed, accessibility2–3 days
7. LaunchDomain, final check, monitoringone day

For a standard store, the stages overlap and the total is 2–4 weeks. For a fully custom design and integrations with other systems, 4–8 weeks. The exact timeline is agreed in writing at the start.

Four-week Gantt chart for a standard store: discovery and design first, setup, products and content in weeks 2–3, apps and integrations, testing in week 4 and launch at the end. Complex projects take 4–8 weeks.
The stages of a standard store over 4 weeks.

What delays a project

  • Content isn't ready: product copy, photos, logo, information for legal pages.
  • Slow feedback: every day waiting for an approval moves the launch.
  • New requirements mid-project: they add time and cost; better to note them for phase two.
  • Integrations with external systems: they depend on the vendor's documentation and response time (ERP, carrier, invoicing).
  • Payment account verification: Shopify Payments and other providers verify your business before you can take payments.
  • Domain access: registrar login details must be available on launch day.

What's included in a professional Shopify setup

Here is what you should get from whoever builds your store:

  • Design built around your brand, not a generic theme with your logo on top.
  • Products, variants, metafields and collections set up and organised properly.
  • The right apps installed, configured and tested: analytics, email, reviews, upsells.
  • Payments and shipping: Shopify Payments, PayPal and local providers, shipping zones and rates.
  • Mobile-first build, with every page tested on a phone.
  • Launch check: taxes, legal pages, checkout flow, notifications.
  • SEO basics: meta titles and descriptions, URL structure, structured data and, when migrating, 301 redirects for every old URL.
  • Work on a development theme or store, so you can review at any time without affecting the live store.

At Horcrux, a build includes the design, products and collections, apps, payments and shipping, mobile testing and the launch check, all in a private development environment. What exactly is in your project is written in the quote.

What a setup usually doesn't include

  • the Shopify subscription, premium theme and paid apps, which you pay directly;
  • product photography and copywriting, unless explicitly requested;
  • marketing campaigns after launch;
  • changes after the included support period, which are billed hourly or through a maintenance plan.

How to shorten the timeline: have copy and photos ready before you start, name one person who approves, and split features into "needed at launch" and "after launch".

Costs for each option are in the guide to what a Shopify store costs, and service details on the Shopify store build page.

Want an exact quote for your store?
Free, within 24 hours.

Tell me what you sell and what you need. I'll tell you what it costs and what you can skip.

Frequently asked questions

A standard store on a well-chosen theme takes 2–4 weeks. Projects with custom design and integrations with other systems take 4–8 weeks.

Design adapted to your brand, organised products and collections, configured apps, payments and shipping, mobile testing, SEO basics, a launch check and work on a development copy.

Content that is not ready (copy, photos), slow feedback, new requirements added mid-project, integrations with external systems and payment account verification.

A products-only migration of a few hundred products usually takes a few working days. Large catalogues with order history and many integrations can take one to two weeks or more.